Gypsum board equipment
equipment category: providing system, making system, transferring system, breaking system, delivery system, drying system, fix-ed cutting system, electrical control system
equipment output: 1-20millions M2/year
fuel types: coal, natural gas, oil
raw materials: land plaster, guarding tissues, water, starch, vesicant
Gypsum board equipment construction conditions
|
Drying types |
Frequency |
Pressure |
Equipment output |
rooms |
Drying room |
Layer |
Capacity |
|
Hot blast drying |
50HZ |
380V |
100万M2 |
10M*70M |
45M |
4 |
55KW |
|
50HZ |
380V |
200万M2 |
10M*80M |
50M |
4 |
90KW |
|
50HZ |
380V |
300万M2 |
10M*90M |
50M |
6 |
100KW |
|
50HZ |
380V |
400万M2 |
10M*110M |
60M |
6 |
120KW |
|
50HZ |
380V |
500万M2 |
10M*120M |
70M |
6 |
150KW |
|
50HZ |
380V |
600万M2 |
10M*140M |
90M |
6 |
170KW |
|
Hot conductive oil drying |
50HZ |
380V |
600万M2 |
10M*140M |
90M |
6 |
370KW |
|
50HZ |
380V |
800万M2 |
10M*190M |
110M |
8 |
370KW |
|
50HZ |
380V |
1000万M2 |
10M*210M |
170M |
10 |
420KW |
Consumption Comparable Table
|
names of materials |
Each dosage |
|
Paper |
1.587KG |
|
Land plaster |
19.5KG |
|
Water |
14KG |
|
Starch |
0.15KG |
|
Vesicant |
0.13KG |
|
Glue |
0.07KG |
|
Power |
0.5KW |
|
Coal |
2.75KG(6000Kcal) |
Sketch map of gypsum board production line
Process of Gypsum board production line
Stock:
Put quantitative modified starch, retarder, pulp and water into hydraulic pulper machine to form raw material pulp. Then pump it into the reserved tin; Put proportional foam and water into foam tin. After churning up the mixture well-proportioned, pump it into the foam reserved tin; Gypsum powder through transmission equipment into the reserved tin;
Batching:
After measurement, all the supplies are pumped into the blender. Mixed to qualified gypsum slurry.
Molding transmission:
Put the opened upper and lower paper into the forming machine. While the lower paper with the slurry from vibrative platform enters the forming machine, too. Squeezed the eligible gypsum board on forming machine, finished early concreting on solidification belt, finished last concreting on transmission belt, cut into the needed length by fixed-cutting machine, turned to the lateral shift system, and left the lateral shift machine. Then enter the drying room through dispensatory machine.
Board releasing unit:
After drying, board released machine finished fix-cutting, packaging, stacking, then transported to a packing tested district. All process end.
| Post Date: | 2/20/2009 |
| Expiry Date: | 2/15/2010 |